Oct 31, 2018 | , ,

39 Wicca Street, Rivervale – Project Update October 2018

Since our last update we have been in a holding pattern waiting for the development application to be assessed by the City of Belmont.

We are still hopeful that the assessment will be completed prior to 20 November, which is the statutory 60 day time-frame from the date of lodgement.

We have been in communication with the Council and at their request have made a number of minor amendments to the plans.

We believe these amendments and the overall plans have been well received by the Council and therefore we have no reason to believe at this point in time that development approval won’t be granted.

I look forward to updating you next month, by which time the Council should have completed its assessment of the development application. Should you have any queries in the meantime please feel free to contact me on (08) 6144 0700 or 0451 533 440.

Regards,
Travis McKenzie