May 31, 2016 | ,

Almond Lane, Ardross – Project Update May 2016

Good progress was made on site during the month of May. Brickwork is now complete on the rear building and all window and door frames have been installed to the apartments.

The 1st floor slab was poured to the front townhouses and work will commence shortly on the brickwork of the top floor.

Work will also commence shortly on the roof framing to the apartment building.

We look forward to updating you on progress next month. At this stage there is no change to our expected completion date which remains at December this year. If you have any questions, please don’t hesitate to call.

Matt Evans

Almond Lane site works9 May 2016 Almond Lane site works8 May 2016 Almond Lane site works7 May 2016 Almond Lane site works6 May 2016 Almond Lane site works5 May 2016 Almond Lane site works4 May 2016 Almond Lane site works May 2016 Almond Lane site works1 May 2016 Almond Lane site works2 May 2016 Almond Lane site works3 May 2016