Jun 30, 2020 | ,

Anzac Road, Mount Hawthorn – June Update 2020

During June the bricklayers were able to finish the first floor party walls and facades for the four rear townhouses. The lightweight internal walls were then constructed which will allow the roof framing to commence next week.

The bricklayers are now waiting for some clear weather so they can finish the front two townhouses.

The focus during July will be to hopefully achieve roof cover on the four rear townhouses and to make good progress towards roof cover on the front two townhouses.

I look forward to updating you next month, however, should you have any queries in the meantime please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

Regards,
Travis McKenzie