Apr 30, 2018 | ,

4 Downey Drive, Manning – Project Update April 2018

Work onsite slowed for the majority of April while the builder waited for the first floor slabs to finish curing.  As soon they were able to, the bricklayers mobilised back to site and commenced constructing the first floor walls.  The bricklayers have commenced at lot 5 and are working their way forward to lot 1.

The focus for May will be to finish the construction of the first floor walls and then the roof carpenters will commence framing up the roofs.

Construction is still on schedule with practical completion anticipated for December this year.

I look forward to updating you next month, but should you have any queries in the meantime, or would like to talk to one of our sales agents about securing one of the apartments or townhouses, please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

 

Regards,

Travis McKenzie