Feb 28, 2020 | ,

Erindale Road – February Update 2020

During February the roof was completed, the windows installed and external doors hung. This has allowed the cafe and equipment rooms to achieve lock up.

The electricians have now installed the distribution board and are roughing in the electrical wiring throughout the building. Hanging of the wall sheeting has also commenced.

The builder is aiming to achieve practical completion by the end of March, at which point Magic Hands will take possession and complete their fitout.

I look forward to updating you next month, however, should you have any queries or would like to lease one of the remaining food tenancies please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

Regards,
Travis McKenzie