May 01, 2020 | , ,

Lucent Claremont – April Update 2020

We continue to make excellent progress completing the building structure at Lucent Claremont.

Work commenced this week forming up the Penthouse deck with the building scheduled to top out in May.

Internally the basement levels, ground and first floors have had the formwork stripped and wall framing on level one will commence this week. Work has also begun on the plumbing stacks and window frame installation on level one.

The builder and developer are continuing to closely monitor supply chains that have been impacted by Covid-19 but at this stage we appear to be managing delivery schedules that will allow construction to progress without significant delay.

We will continue to monitor this closely however and contingency plans have been prepared for key risk areas.

We look forward to updating you as the building progresses

Regards,
Matt Evans