Vic Quarter – Project Update April 2019

We are pleased to report that great progress is being made at Vic Quarter as the building moves toward completion in September this year.

Level one apartments are now nearing completion with just flooring and a final paint coat required internally.
The balconies have been tiled and now just require balustrades and planter boxes to be installed.

On the second level, kitchens are now also complete and work has commenced on the plumbing fit-out with toilets, basins and shower screens being installed.

On level three over half the kitchen cabinets have been installed with stone installation to commence next week.

On level four all walls and ceiling are now lined and installation of window frames has commenced.

Level five has all stud walls now installed and the roof is complete on the Northern end of the building.

The penthouse level now has party walls completed and the structural steel for the roof is also in place.

The finishing trades will now continue to work their way up the building.

We look forward to updating you with further progress next month.

If you have any questions or would like to find out more about Vic Quarter, please feel free to call me directly on (08) 6144 0700 or 0401 009 617.

Regards,
Matt Evans