125 Bank Street – August Update 2021

In last month’s update I reported that the last remaining slabs were about to be poured, loaded with bricks and after a fortnight the bricklayers were to commence. I’m pleased to report that the slabs were poured on time and were loaded with bricks. However, the bricklayers who were due to start on the project were delayed from finishing off another project and consequently did not commence until August 30th.

The focus for September will be to complete as much of the brickwork as possible and hopefully commence the roof framing on some of the villas. As always, weather will play a big role in how much progress the bricklayers are able to make.

The builder is currently aiming to achieve practical completion in late February 2022.

I look forward to updating you next month, but in the meantime should you have any queries please feel free to contact me on (08) 6144 0700 or 0451 533 440.

 

Regards,
Travis McKenzie