39 Wicca Street, Rivervale – Project Update July 2019

During July we continued to see wet weather but fortunately there were enough dry spells to allow the bricklayers to complete the first floor walls of the two townhouses.

The roof carpenters were then able to construct the roof frame and roof sheeting, and gutters are now being installed and should be fully completed by the end of July.

With roof cover on, this will allow the plumbers and electricians to come back to site and chase in their conduits and pipes.

Once that is completed then the remaining part of August will be taken up with the internal float coat being applied to the walls.

I look forward to updating you next month, however, should you have any queries in the meantime, please feel free to contact me on (08) 6144 0700 or 0451 533 440.