Apr 30, 2018 | , ,

Vic Quarter – Project Update April 2018

We are pleased to report that construction is progressing well on site.

The tower crane has now been fully installed which is allowing work to progress more efficiently on site. The first section of the basement slab has been poured and the formwork for the ground floor slab in the Southwest corner of the site has now been installed for the slab to be poured later this week. The final section of basement retaining walls have also been installed at the rear of the site and the builder will now complete the remainder of the basement slab working their way from the Southwest corner.

We look forward to updating you as the development progresses.

Matt Evans