Celsius Land May Update

Project Update – Celsius Living – Piara Waters  

The last 3 lots in the project have been sold with two lots due to settle in June 2025 and one sale still subject to a contract condition. Celsius is excited to have welcomed our first residents who moved into their new home in May 2025. With the onset of winter rains, planting in the public open space drainage basins will soon be undertaken.

 

Project Update – Celsius Living – Champion Lakes

Construction works in stage 1 (54 lots) are anticipated to reach practical completion on 6 June 2025. Final clearances are being sought with titles expected to issue in early July 2025. Stage 2 construction works are expected to commence in September / October 2025 with a sales release also expected around this time. The public open space landscaping will be tendered during the months of June / July 2025 with landscaping works due to commence in August / September 2025.  Sales are well progressed with only 5 lots remaining for sale in stage 1.

Project Update – Exmouth Marina land and housing development

Celsius Land is project managing the residential development of the remainder of the Exmouth marina. The town planning scheme amendment for the rezoning of the site to Urban Development was supported by the Shire of Exmouth Council on 29 May 2025 and will now be considered by the Western Australian Planning Commission. Engineering design is well underway and the next step is lodgement of the subdivision application with the WAPC. The development, which will comprise approximately 157 residential lots along with 15 commercial sites, will provide much needed residential land and housing to Exmouth in an ideal location adjacent to the marina. Construction and sales of stage 1 is due to commence later in the year. If you would like to register your interest to receive further information please email Mark Lucas at Ray White Exmouth mark@raywhiteexmouth.com